If the Judge's ruling blocking the construction of the Sunrise Powerlink through the Southern Californian desert, due to possible environmental damage, is upheld, it could doom the second phase of a massive 850 MW solar project. The project is among the first Stirling engine-driven solar farms, as pictured here.  (Source: Sterling Energy Systems)
The effort to tap solar energy in California's desert is grinding to a halt

California has long led the nation's solar efforts.  However, it is facing increasing legal pressure as the state's environmentalists clash over whether installing solar power is worth possible environmental damage.

The conflict was brought into sharp focus when activist judge Jean Vieth, an administrative law judge with the California Public Utilities Commission, struck down plans to build a high power transmission line from the remote Californian desert, effectively dooming the massive solar initiatives set to be built in the desert.

The desert project was a joint initiative by San Diego Gas & Electric and Phoenix-based Stirling Energy Systems signed in 2005.  It aimed to install 900 MW of Stirling solar power in uninhabited Southern Californian desert wasteland.  Stirling power is a method of concentrating sunlight with mirrors onto water fueling a Stirling engine, and is thought to possibly yield higher efficiencies than photovoltaic cells.  The plant would feature 34,000 dishes, each generating 25 kW.

Central to the plan was the construction of a suitable power transmission line.  SDG&E had partnered with Sterling Energy Systems to create the Sunrise Powerlink a $1.3B USD power line to bring the solar power to Californian cities.

The project was struck down by Judge Vieth, who argues that its 150-foot-high transmission towers, which would cut through Anza-Borrego State Park, could be environmentally damaging.  The park features many protective species and Judge Vieth calls the power lines impact "frightening".

The project has generated an 11,000-page environmental impact report, which is so long that few have taken the time to read it all.  Judge Vieth's decision alone was 265 pages.  In it she wrote, "The potentially high economic costs to ratepayers and the potential implications for our [greenhouse gas] policy objectives do not justify the severe environmental damage that any of the transmission proposals would cause."

The fight is far from over, though.  The public utilities commission meets in December to vote on whether to accept the Judge's ruling.  A commissioner assigned to review the case created an alternative, which they are also considering.  The alternative would be to move the route of the transmission line slightly, increasing costs, but potentially having less environmental impact.

Opponents of the project have argued that San Diego, the target for most of the generated power, already has enough rooftop space for urban installation of an equivalent solar installation.  The Judge has stated that she prefers this alternative.

COO Bruce Osborn previously stated to The Green Wombat, an online publication, that even if the Sunrise Powerlink was killed, there was still enough capacity to carry the 300 MW from the first phase of the project.  However, this will likely place more stress on California's already badly aging power grid.  Stirling still has its 20-year contract to supply up to 850 megawatts of electricity to utility Southern California Edison, a deal entirely unrelated, to fall back upon.

The case, while far from finished, illustrates an upcoming battle to be waged among once-allies.  As our nation embraces alternative energy, part of President-elect Barack Obama's ambitious national initiative, there will likely be increasing clashes between environmentalists supporting alternative energy installation, and those opposing it for possible environmental damage.



Comments     Threshold


This article is over a month old, voting and posting comments is disabled

RE: ...and it starts
By Keeir on 11/6/2008 1:37:53 PM , Rating: 5
And yet...

Applications to build new nuclear plants and extend lifespan of existing plants in the US are at a 20+ year high

Companys that make major Nuclear Plant subsystems have more orders than capacity to produce

Nations such as China are expanding Nuclear Capacity faster than any other source (China is also rapidly expanding Coal, Wind, and Hydro, but Nuclear surpasses each of these individually)

I think the Free Market has spoken, There is a significant case for Nuclear Power. Especially when compared to 15 cent per kWh Wind and 30+ kWh Solar.

Lastly, "Fuel Reprocessing is unproven and extremely expensive"

Last I checked, in 1976 India was able to use reprocessing technologies to create Nuclear Weapons (the possibility of which is the reason the US does not reprocess our Nuclear waste). France, Britian, and Japan have together 7 major reproccessing facilities. Sorry, these nations all find reprocessing to be acceptable in large scale.


RE: ...and it starts
By andrinoaa on 11/6/08, Rating: -1
RE: ...and it starts
By Spuke on 11/6/2008 5:30:30 PM , Rating: 2
quote:
The waste issue still has not been resolved.
I hate it when people can't read. The waste issue HAS been resolved through the use of newer technologies. Do some reading on the countries that presently use nuclear energy.


RE: ...and it starts
By Keeir on 11/6/2008 6:50:44 PM , Rating: 3
What you mean is none have been built where you can see them..

China plans to building 10-100 reactors in the next 20 years. I believe it has more than 20 under construction right now at around 10 sites.

France, US, Japan, Russia, Brazil, India, Pakistan, Iran, (the list goes on) either have plants under contrustion or plans awaiting regulatory approval.

The company that produces the Reactor chamber for the Westinghouse AP1000 will have new compedition because it simply can't produce enough parts...


"If you mod me down, I will become more insightful than you can possibly imagine." -- Slashdot














botimage
Copyright 2014 DailyTech LLC. - RSS Feed | Advertise | About Us | Ethics | FAQ | Terms, Conditions & Privacy Information | Kristopher Kubicki